Early Projects
With Saudi Electricity Company - Eastern Region Branch
|
Expansion of 230 kV GIS double bus configuration at Qatif, Thuqbah
and Dammam BSP comprising of following SF6 gas insulated metal enclosed
equipment.
Complete
with Lead control, Remote control, breaker failure, Bus bar protection,
relaying and metering system and expansion of SCADA, SOE and Digital fault
recorder system.
Expansion of 230kV Hawiyah BSP Complete
installation, testing & commissioning of outdoor substation with all
its related Control & Protection, Relaying and Metering equipments
comprising of following.
Supply & Installation of complete HVAC system including equipments and controls at 380/230KV Al-Fadhili Substation and Modification of existing S/S.
Complete Supply, Installation and commissioning the HVAC system including lighting system at 230KV Jubail South-East expansion of control Building.
Complete supply of electrical material, labor and equipment, testing and commissioning of electrical system including complete installation, testing and commissioning of HVAC equipments (Package Unit) at Nariyah office complex.
Complete installation, supply, testing and commissioning of HVAC Equipments (Package Unit) at 69/13.8KV Bohairah S/S, reinforcement of Meridian S/S.
Next => |
||||||||||||||||||||||||||||||||||||||||
| Copyright ©
1999-2002 EPE - Energy & Power Contracting Co. Ltd. All rights reserved. For more information, contact us: info@epe.com.sa Designed and Hosted by SiteSaudia |
||||||||||||||||||||||||||||||||||||||||